Lincoln/Washington Student Room & Restroom Renovation

In an effort to keep projects progressing on campus during a time when finances are being closely monitored, we have scaled back the project so that it can continue. UHDS is now utilizing the WIU Physical Plant Construction Crew to do all student room and lounge work. Due to the size and scope of the work and to keep the facility operational during the academic year, construction will be done 2 floors at a time. Upon completion of a floor, residents will be asked to move up 2 floors from their existing room. Abatement will also be occurring throughout the year so that we can turn over the building to the contractor for the first bathroom renovation at the end of May. We realize this is an inconvenience to many, but hope that residents will understand as this allows us to continue with the project.

Photo Gallery of Project Progress



Scope

  • New paint in student rooms, lounge, hallways, and stairwells
  • Replacing student room furniture (with the exception of the existing built-in dresser)
  • Adding wireless capability throughout the residence hall (summer 2011)
  • Addressing several maintenance items
  • Re-Insulating piping throughout residential floors
  • Adding overhead lighting in student rooms
  • Adding outlet receptacle to each room
  • Conversion of 2 student rooms into new floor lounge
  • Complete renovations of bathrooms (summers of 2011 and 2012)

3-D Rendering of New Restroom

(actual colors and finishes may be different than shown in rendering)


Floor Plans (Before /  After)

Lincoln/Washington Floor Plan Before    Lincoln/Washington Floor Plan After

New Student Room Furniture Included in Project

New Bed in Lincoln/Washington Rennovation

 

 

        New Desk in Lincoln/Washington Renovation

 

Bed (height adjustable to multiple levels)                         Desk w/ side-table shown

 

New Enterntainment Stand in Lincoln/Washington Rennovation

Entertainment Stand

Timeline

The Lincoln/Washington Hall renovation project was  completed over a period of 2 years, with overall completion in August 2012. Washington Hall student rooms and lounge were renovated during the 2010-2011 academic year and Lincoln Hall student rooms and lounge were renovated during the 2011-2012 academic year. Bathroom renovations were scheduled for Washington (summer 2011) and Lincoln (summer 2012).

Costs

$500,000/Tower for room renovations.
$2,700,000/Tower for bathroom renovations

Contractors

  • Architect: BLDD Architects, Bloomington, IL (Bathroom Renovations)
  • General Contractor: WIU Physical Plant (Student Room Renovations), Williams Brothers Construction, Inc. Peoria, IL (Bathroom Renovations)
  • Electrical Contractor: WIU Physical Plant (Student Room Renovations), Mechanical Services, Inc. Galesburg, IL (Bathroom Renovations) 
  • Heating/Mechanical Contractor: WIU Physical Plant (Student Room Renovations), Mechanical Services, Inc. Galesburg, IL (Bathroom Renovations) 
  • Plumbing Contractor: Warner Plumbing East Peoria, IL (Bathroom Renovations)